Thailand Government Emergency Drainage Project in 2012 | DEFU
High-Performance Pump Solution for New Zealand Cooling System in 2022
June 5, 2025

Thailand Government Emergency Drainage Project in 2012

Project Background:

In February 2012, the Thailand Government approached us with a critical requirement: a high-capacity 12-inch drainage pump capable of handling 1,250 m³/h at 11m head, equipped with a vacuum-assisted self-priming system for rapid flood response.

 

Challenge:

  • High-flow, low-head demand for efficient monsoon-season flood control
  • Instant self-priming capability for emergency deployment
  • Continuous heavy-duty operation under extreme weather conditions
  • Quick installation & automated control for immediate response

 

Our Solution:

  1. High-Efficiency Pump Design
  • Horizontal split-case double-suction pump – Optimized for high flow & low head
  • Anti-cavitation impeller design – Ensures longer lifespan under demanding conditions
  1. Rapid Self-Priming System
  • Integrated vacuum assist-Ensures fast start capability
  1. Smart Automated Control
  • Intelligent control panel featuring:
  • Water-level activated start/stop
  • Real-time fault monitoring
  • Remote operation interface
  1. Rapid Deployment Package
  • Fully skid-mounted system (diesel engine pump+ vacuum system + control panel)
  • Pre-assembled & tested for 24/7 rapid deployment

 

Performance Results:

✔ 12-hour floodwater clearance in critical urban zones

✔ 30% faster priming vs. competitor pumps (validated by field testing)

✔ Zero failures during 72+ hours of non-stop operation

✔ Seamless integration with municipal flood response protocols

15%

Efficiency Improvement

1250m³/h

Flow Rate

Thailand Government Emergency Drainage Project in 2012

TPOW Split Case Double Suction Pump Catalogue

Tell Us What You Need

    Get A Quote